PN-24-03 NAB-2023-61604-P33 (Jug Bay Sanctuary Living Shoreline)

USACE
Published Jan. 23, 2024
Expiration date: 2/22/2024

                   Public Notice
U.S. Army Corps                In Reply to Application Number
of Engineers                        NAB-2023-61604-P33 (Jug Bay Sanctuary Living
                                                Shoreline)

Baltimore District
PN-24-03                               Comment Period: January 23, 2024 to February 22, 2024
THE PURPOSE OF THIS PUBLIC NOTICE IS TO INFORM INTERESTED PARTIES OF THE PROPOSED ACTIVITY AND TO SOLICIT COMMENTS. NO DECISION HAS BEEN MADE AS TO WHETHER OR NOT A PERMIT WILL BE ISSUED AT THIS TIME.

This District has received an application for a Department of the Army permit pursuant to Section 10 of the Rivers and Harbors Act (33 USC 403) and Section 404 of the Clean Water Act (33 USC 1344),as described below:

APPLICANT:

Anne Arundel County (Jug Bay Wetlands Sanctuary)
1361 Wrighton Road
Lothian, MD 20711

WATERWAY AND LOCATION OF THE PROPOSED WORK:

The proposed project is located in Patuxent River, in Lothian Anne Arundel County, Maryland (38.774773, -76.704849)

OVERALL PROJECT PURPOSE:

To provide shoreline erosion control and establish/enhance habitat.

PROJECT DESCRIPTION:

The applicant proposes, in accordance with the attached plans, to stabilize the shoreline approximately 411 linear feet of shoreline utilizing a living shoreline design by emplacing a series of four (4) shore connected headland control vegetated breakwater structures, all within an approximately 13,974 square foot or 0.32 acre impact area as follows: to construct a 102-foot long by 34-foot wide stone breakwater (breakwater 1), to construct a 65-foot long by 34-foot wide stone breakwater (breakwater 2), to construct a 106-foot long by 34-foot wide stone breakwater (breakwater 3), to construct a 104-foot long by 34-foot wide stone breakwater (breakwater 4), all not to exceed 100 foot channelward of the approximate mean high water line: 8 woody habitat structures within the breakwater structures, to emplace approximately 2,011 cubic yards of sand with approximately 364 linear feet and 14,444 square feet of marsh terrace with high (S. patens) /low (Spartina alterniflora) marsh plantings not to exceed 68-feet channelward of the mean high water line, and to create a 1,450 square feet pocket beach with 50 cubic yards of sand fill not to exceed 45-feet channelward of the mean high water line: all within the area of each of the four above-described breakwaters.

All work is proposed in accordance with the attached plans prepared by Bayland Consultants & Designers, Inc. dated October 2023.

EFFECTS ON AQUATIC RESOURCES:

Proposed Activity

Aquatic Resource Impact (sf)

Aquatic Resource Type

Authority

Breakwater/Pocket Beach

27,949

Tidal Waters

Section 10/404

Total:

27,949

 


LEAD FEDERAL AGENCY:

The United States Army Corps of Engineers, as the lead federal agency, is responsible for all coordination pursuant to applicable federal authorities.

APPLICANT’S PROPOSED AVOIDANCE, MINIMIZATION, AND COMPENSATORY MITIGATION:

As part of the planning process for the proposed project, steps were taken to avoid and minimize impacts to aquatic resources to the maximum extent practicable based on the existing site conditions. The applicant proposes to avoid and minimize impacts by designing the headland breakwaters to be of the minimum channelward extent necessary to provide reduced wave energy and erosion rates.

No compensatory mitigation is currently proposed. The project would result in the establishment of approximately 11,728 sf of low marsh vegetation (Spartina alterniflora) and 13,156 sf of high marsh vegetation (S. patens) with the vegetated breakwaters and marsh terrace. The applicant designed the proposed ratio of low to high marsh vegetation to mimic the natural shorelines more closely, which tend to be dominated by S. patens and beach strand habitat.

CORPS EVALUATION REQUIREMENTS:

This project will be evaluated pursuant to Corps Regulatory Program Regulations (33 CFR Parts 320-332). The decision whether to issue a permit will be based on an evaluation of the probable impacts, including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit, which reasonable may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors, which may be relevant to the proposal will be considered, including the cumulative effects thereof; among those are conservation, economic, aesthetics, general environmental concerns, wetlands, cultural values, fish and wildlife values, flood hazards, flood plain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, and consideration of property ownership and in general, the needs and welfare of the people. The evaluation of the impact of this project will also include application of the Clean Water Act Section 404(b)(1) Guidelines promulgated by the Administrator, United States Environmental Protection Agency.

ENDANGERED SPECIES:

A preliminary review of this application indicates that the proposed work is not likely to adversely affect federally listed threatened or endangered species or their critical habitat, pursuant to Section 7 of the Endangered Species Act, as amended. As the evaluation of this application continues, additional information may become available which could modify this preliminary determination.

ESSENTIAL FISH HABITAT:

The Magnuson-Stevens Fishery Conservation and Management Act (MSFCMA), as amended by the Sustainable Fisheries Act of 1996 (Public Law 04-267), requires all federal agencies to consult with the National Marine Fisheries Service on all actions, or proposed actions, permitted, funded, or undertaken by the agency that may adversely affect Essential Fish Habitat (EFH), including species of concern, life cycle habitat, or Habitat Areas of Particular Concern. The project site lies in or adjacent to EFH as described under MSFCMA for managed species under the MSFCMA. The Baltimore District has made a preliminary determination that the project will not have a substantial adverse effect on EFH. The Baltimore District has made a preliminary determination that mitigative measures are not required to minimize adverse effects on EFH at this time. This determination may be modified if additional information indicates otherwise.

HISTORIC RESOURCES:

Pursuant to Section 106 of the National Historic Preservation Act of 1966 and applicable guidance, the Corps has reviewed the latest published version of the National Register of Historic Places and initially determined that no registered properties listed as eligible for inclusion, therein, are located at the site of the proposed work. The Corps has made the preliminary determination that the proposed project would have no adverse effect on historic properties. The Corps final eligibility and effect determination will be based on coordination with the State Historic Preservation Office as appropriate and required, and with full consideration given to the proposed undertaking’s potential direct and indirect effects on historic properties within the Corps’ identified permit area.

TRIBAL RESOURCES:

Section 106 of the National Historic Preservation Act also requires federal agencies to consult with federally recognized American Indian tribes that attach religious and cultural significance to historic properties that may be affected by the agency’s undertaking. Corps Tribal Consultation Policy mandates an open, timely, meaningful, collaborative, and effective deliberative communication process that emphasizes trust, respect, and shared responsibility. The policy further emphasizes that, to the extent practicable and permitted by law, consultation works toward mutual consensus and begins at the earliest planning stages before decisions are made and actions taken. The Corps final eligibility and effect determination will be based on coordination with interested tribes, in accordance with the Corps current tribal standard operating procedures as appropriate and required, and with full consideration given to the proposed undertaking’s potential direct and indirect effects on tribal resources.

MODIFICATION OF CIVIL WORKS PROJECTS: 33 USC 408 (SECTION 408):

All Section 408 proposals will be coordinated internally at the United States Army Corps of Engineers. The Section 408 decision will be issued along with the Section 404 and/or Section 10 decision. Please see the following link for more information regarding Section 408: https://www.nab.usace.army.mil/Missions/Regulatory/Section-408-Requests/.

WATER QUALITY CERTIFICATION:

The applicant is required to obtain a water quality certification in accordance with Section 401 of the Clean Water Act.=

COASTAL ZONE MANAGEMENT PROGRAMS:

Where applicable, the applicant has certified in this application that the proposed activity complies with and will be conducted in a manner consistent with the approved Coastal Zone Management Program. By this public notice, we are requesting the state concurrence or objection to the applicant’s consistency statement.

The applicant must obtain any state or local government permits which may be required.

SUBMISSION OF COMMENTS:

The Corps of Engineers is soliciting comments from the public; federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. Comments provided will become part of the public record for this action and are subject to release to the public through the Freedom of Information Act. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

Written comments concerning the work described above related to the factors listed above or other pertinent factors must be received by the United States Army Corps of Engineers, Baltimore District within the comment period specified above through postal mail at the address below or electronic submission to the project manager email address below. Written comments should reference the Application Number NAB-2023-61604-P33 (Jug Bay Sanctuary Living Shoreline).

 PUBLIC HEARING REQUESTS:

Any person who has an interest which may be adversely affected by the issuance of this permit may request a public hearing. The request, which must be in writing, must be received within the comment period as specified above to receive consideration. Also, it must clearly set forth the interest which may be adversely affected by this activity and the manner in which the interest may be adversely affected. The public hearing request may be submitted by electronic mail or mailed to the following address:

Alicia Palmer
alicia.e.palmer@usace.army.mil
United States Army Corps of Engineers, Baltimore District
Regulatory Branch
1631 South Atherton Street
State College, PA 16801

It is requested that you communicate this information concerning the proposed work to any persons known by you to be interested, who did not receive a copy of this notice.

General information regarding the Corps’ permitting process can be found on our website at https://www.nab.usace.army.mil/Missions/Regulatory.aspx. This public notice has been prepared in accordance with Corps implementing regulations at 33 CFR 325.3. If you have any questions concerning this specific project or would like to request a paper copy of this public notice, please contact Alicia Palmer, 814-235-1764, and alicia.e.palmer@usace.army.mil. This public notice is issued by the Chief, Regulatory Branch.