US Army Corps of Engineers
Baltimore District

Announcements

Recent Public Information Sessions

On-Post Public Info Session

January 28, 2019

Thurman Hall (Bldg. 247)
Fort Belvoir, VA

Presentation available here

 

 
 
Off-Post Public Info Session

March 12, 2019
(rescheduled from January 29th for weather)

Fairfax County's South County Government Center

Presentation available here

Posters available here

 

Contract Acquisition Process

The project team is working with our planning contractor and will be working with the external stakeholders and interested parties as we proceed with our planning efforts. Additionally, the project team has started the contract acquisition process for the next phase of work - which would be the Decommissioning Implementation. 

Click here for a broad overview of the contract acquisition approaches for the decommissioning of both the SM-1 (Fort Belvoir) and SM-1A (Fort Greely, Alaska) reactors (Information in presentation is as of March 2018). All inquiries regarding contracting opportunities should be directed to James Greer via email to James.A.Greer@usace.army.mil.  Additional updates will be posted as the project progresses.  

The next major step for the SM-1 decommissioning will be consultation with stakeholders, including the public and the Fort Belvoir community, for the Environmental Assessment Report. 

SM-1: August 25, 2019 Stakeholder Update

Dear SM-1 Stakeholders,

The U.S. Army Corps of Engineers released the Request for Proposal (RFP) notice earlier today for the contract for the decommissioning and dismantling of the SM-1 deactivated nuclear power plant at Fort Belvoir. With the release of the RFP, the team remains on schedule to award a contract for this work in the latter half of 2020.

A site visit will be held for all potential bidders on September 16, 2019.  Additional information pertaining to this RFP and how potential bidders can participate in the site visit can be found on FedBizOpps at –  https://www.fbo.gov/spg/USA/COE/DACA31/W912DR18R0021/listing.html

Additionally, the project team continues to work on the Decommissioning Planning documents, to include the Decommissioning Plan and the Environmental Assessment.  The team appreciates the feedback we received from members of the community, both on-post and off-post, earlier this year. We anticipate publicly releasing the draft Environmental Assessment later this fall and having a public comment period to allow stakeholders to provide additional feedback. 

Thank you all again for choosing to be a part of this process with us as we continue working through the planning phase of the decommissioning and dismantling of the deactivated SM-1.

As always, additional project information, historical photos, and previous stakeholder updates regarding the SM-1 project can be found on our website: www.nab.usace.army.mil/SM-1/.

If you have any questions, feedback or information you’d like to share with us, please feel free to e-mail me or call our Corporate Communication team at 410-962-2809.

----------

Click here for an archive of previous stakeholder updates

SM-1 Former Nuclear Power Plant Overview

The SM-1 Former Nuclear Power Plant is located on the western shore of the Potomac River within the boundaries of Fort Belvoir in Fairfax County, Virginia. It is approximately 17 miles south by southwest from the center of Washington D.C.

The construction of the SM-1 at Fort Belvoir was completed in 1957, and it achieved its first criticality in April 1957. The SM-1 was a single-loop 10 megawatt-thermal (MWt) pressurized water reactor delivering a net 1,750 kilowatts of electrical power. It was the first nuclear power reactor to provide electricity to a commercial power grid in the United States. The SM-1 Reactor operated from April 1957 to March 1973. Fort Belvoir was home to the U.S. Army Engineer Reactors Group (USAERG), and the SM-1 was used for training the multi-service crews that would operate the various plants in the program. The reactor was stationary with a medium power range, which was between 1,000 and 10,000 kilowatt-electric (kWe).

Deactivation was performed on the SM-1 Reactor from 1973-1974, in accordance with the SM-1 Decommissioning and Conversion Plan as approved by the Army Reactor Systems Health and Safety Review Committee (ARCHS). This consisted of removal of the nuclear fuel, minor decontamination, shipment of necessary radioactive waste, sealing the pressure vessel, and installing appropriate warning signs and monitoring devices.

After the completion of the facility deactivation and conversion, a third party radiological survey by the U.S. Army Environmental Hygiene Agency verified that known areas of radioactive contamination had been decontaminated to acceptable levels or were properly controlled. The ARCHS approved the SM-1 Post-Decommissioning Environmental Monitoring Plan, which has been used to provide on-going surveillance of the decommissioned facility.

In October 1996, the U.S. Army Center for Health Promotion and Preventive Medicine (USACHPPM) took extensive surveys of the SM-1 and surrounding environment to determine the radiological status of the facility at that time. In 2005, a Historical Site Assessment was developed using operational records and data collected from the 1996 USACHPPM Surveys. In 2009/2010 Characterization Surveys were completed and the Report was finalized in 2013.

The Historical Site Assessment and Characterization Surveys support the decommissioning study process outlined in Army Regulation 50-7. This process is performed by USACE, at the direction of the Army Reactor Office, to better define disposal activity costs.

The decommissioning strategy that was developed in the 1970's recommended that the deactivated reactors be placed into a safe storage mode that would allow the shorter-lived radionuclides to decay. It was expected that delaying decommissioning would reduce radioactive waste volumes and worker exposures. However, subsequent studies indicated that the levels of contamination present within the reactors would not be reduced by decay sufficiently to allow for release of the facilities without significant decontamination being performed. Additionally, concern regarding the increasing cost and decreasing availability of radioactive waste disposal led the Army Reactor Office (ARO) to recommend that an assessment be performed of the SM-1 reactor. The assessment allowed for a more accurate decommissioning cost estimate, which addresses projected changes in disposal options.

USACE developed a management plan for conducting an All Hazards Assessment, which contained provisions for four phases of work to be performed. Phase I included a Historical Records Review and Disposal Alternatives Investigation. Phase II, included performing a characterization survey and decommissioning cost estimate. Phases III and IV deal with decommissioning planning, design, and execution.

Join Our Stakeholder List

Receive the latest updates regarding the former SM-1 Nuclear Power Plant by entering your information below to join our stakeholder list. 






*
SM-1 was a 2-megawatt nuclear reactor developed by the United States Atomic Energy Commission for the US Army Nuclear Power Program (ANPP) in the mid-1950s.
Undated - Technicians set the core structure for the Army Package Power Reactor. At this stage, the reactor plant was 96 percent complete.(Photo courtesy of the Office of History)
A Soldier reads an informational handout about the ongoing planning for the final decommissioning and dismantling of the Deactivated SM-1 Nuclear Power Plant at Fort Belvoir during the Army Aviation Brigade's Safety Stand Down at Davison Army Airfield Thursday May 23, 2019. The SM-1 project team participated in the event as part of ongoing outreach efforts to inform members of the Fort Belvoir community about the SM-1 project, help create an understanding of the nature of the project and address potential concerns. More information about the SM-1 project is available online at www.nab.usace.army.mil/SM-1
Undated - Appears to be construction and installation of reactor at SM-1. (Photo courtesy of the Office of History)
Retired Lt. Gen. Ernest Graves and his wife Nancy Graves discuss his past experiences with the military’s application of nuclear power, including his role in the completion and initial operation of the first-of-its-kind SM-1 nuclear reactor at Fort Belvoir, with personnel from the Defense Threat Reduction Agency and the U.S. Army Corps of Engineers at the US Army Nuclear and Countering Weapons of Mass Destruction Agency headquarters on Fort Belvoir, Tuesday September 19, 2017. In addition to providing nuclear and countering weapons of mass destruction expertise, USANCA is home to the Army Reactor Office, which issues the permits for the Army’s one operating and three deactivated nuclear reactors.
U.S. Army Corps of Engineers Project Manager Brenda Barber and Radiological Health Physicist Hans Honerlah speak with a civilian attendee at the U.S. Army Aviation Brigade's Safety Stand Down at Davison Army Airfield about the ongoing planning for the final decommissioning and dismantling of the Deactivated SM-1 Nuclear Power Plant at Fort Belvoir Thursday May 23, 2019. The SM-1 project team participated in the event as part of ongoing outreach efforts to inform members of the Fort Belvoir community about the SM-1 project, help create an understanding of the nature of the project and address potential concerns. More information about the SM-1 project is available online at www.nab.usace.army.mil/SM-1
Retired Lt. Gen. Ernest Graves sits at the control panel of the deactivated SM-1 nuclear reactor and power plant at Fort Belvoir during a site visit Tuesday September 19, 2017. As a major with the U.S. Army Corps of Engineers, Graves oversaw the completion of the construction of the facility and its initial operation in the late 1950s. While SM-1’s reactor was deactivated in 1973 and placed into safe storage, the U.S. Army Corps of Engineers is in the process of planning for the reactor’s final decommissioning and dismantlement for the facility. Bringing Graves to the facility served two main purposes:  allowing the team to gather as much information as possible about the construction of the facility; and providing historical context and additional history of SM-1’s operation.
U.S. Army Corps of Engineers Radiological Health Physicist Hans Honerlah speaks with Soldiers at the U.S. Army Aviation Brigade's Safety Stand Down at Davison Army Airfield about the ongoing planning for the final decommissioning and dismantling of the Deactivated SM-1 Nuclear Power Plant at Fort Belvoir Thursday May 23, 2019. The SM-1 project team participated in the event as part of ongoing outreach efforts to inform members of the Fort Belvoir community about the SM-1 project, help create an understanding of the nature of the project and address potential concerns. More information about the SM-1 project is available online at www.nab.usace.army.mil/SM-1

Contact Information

To join our stakeholder list and receive email updates, please call or email us:  

Phone: 410-962-2809
E-mail: cenab-cc@usace.army.mil

Or if you have questions, please don't hesitate to reach out to us. 

Please direct any inquiries regarding contracting opportunities to James Greer via email to James.A.Greer@usace.army.mil.

Project Documents

This section includes the project documents to date.